Question 8
A stadium was to be built in 1500 days. The contractor employed 200 men, 300 women and 750 robotic machines. After 600 days, 75% of the work was still to be done. Fearing delay, the contractor removed all women and 500 robotic machines. Also, he employed some more men having the same efficiency as earlier employed men. This led to a speedup in work and the stadium got built 50 days in advance. Find the additional number of men employed if in one day, six men, ten women and fifteen robotic machines have same work output.